Method of installing prefabricated, segment concrete filled tube members
Seong-woon Kim, Seoul (Korea, Republic of); Young-jin Kim, Gyeonggi-do (Korea, Republic of); In-gyu Kim, Gyeonggi-do (Korea, Republic of); Byeong-moo Jin, Gyeonggi-do (Korea, Republic of); Tae-hoon Kim, Gyeonggi-do (Korea, Republic of); Hyang-wook Ma, Seoul (Korea, Republic of); and Yun-seok Lee, Seoul (Korea, Republic of)
Assigned to Daewoo Engineering & Construction Co., Ltd, Jung-Gu (Korea, Republic of)
Filed on May 10, 2006, as Appl. No. 11/430,860.
Claims priority of application No. 10-2005-0074639 (KR), filed on Aug. 16, 2005; and application No. 10-2005-0121674 (KR), filed on Dec. 12, 2005.
Prior Publication US 2007/0039283 A1, Feb. 22, 2007
Int. Cl. E01D 21/00 (2006.01); E01D 22/00 (2006.01)
U.S. Cl. 14—77.1  [14/75; 14/77.3] 1 Claim
OG exemplary drawing
 
1. A method of supporting a bridge, comprising the steps of:
(a) lifting a prefabricated coping part of the upper portion of a bridge pier;
(b) installing a prefabricated segmental concrete filled tube member under the coping part, the segmental concrete filled tube member including a hollow pipe filled therein with concrete, and a connection flange radially extending from the peripheries of both ends of the pipe;
(c) installing another prefabricated segmental concrete filled tube member under the former prefabricated segmental concrete filled tube member to connect each other such that the connection flange of the latter segmental concrete filled tube member brings in contact with that of the former segmental concrete filled tube member;
(d) injecting a filler material into an injection hole formed by grooves provided on opposite surfaces of the connection flanges, respectively; and
(e) repeating the steps (c) and (d).